Project Overview
EDECS took the lead in managing Phase 2 of the Ahl Misr Walkway Nile RiverCairo project in Egypt, constructing a 1200-m walkway with various amenities along the Nile River. Our work included marine piling and dredging, building construction for the walkway and amenities, electromechanical works covering water supply, drainage, firefighting, and irrigation systems, and electrical infrastructure installation, including transformers, generators, distribution panels, lighting fixtures, and 4 buildings. Additionally, we undertook site landscaping and hardscaping tasks, incorporating stone flooring, steel fencing, stainless steel handrails, and colored concrete pathways.
Project Details:
Client:
Ministry Of Housing, Utilities & Urban Communities
Consultant:
ACE Moharram-Bakhoum
Contract Details:
Role in Contract:
Main Contractor
Contract Type:
Construction
Contract Duration:
9 Months
Completion Date:
July 2021