Project Overview
EDECS embarked on constructing a multi-purpose terminal at Al-Dekheila Seaport, Berth 100. It involves erecting a 1,775-meter diaphragm-type quay wall at a depth of 17 meters. The project encompasses soil improvement utilizing Prefabricated Vertical Drains (PVD), Vibro-compaction (VC), Dynamic compaction (DC), and Rapid Impact Compaction (RIC). Additionally, deep foundation works will be constructed, including diaphragm walls and piles reaching 38 meters. The superstructure will consist of the Back beam, Front beam, and slab. Furthermore, the installation of berth furniture such as Fenders, Bollards, Ladders, Mooring rings, and crane rails spanning a total length of 1200 meters will be completed. EDECS is committed to delivering excellence in every aspect of Al-Dekheila Seaport Berth 100 project, ensuring superior quality and innovation from inception to completion.
Project Details:
Client:
Alexandria Port Authority-Ministry of Transportation
Consultant:
G.C. Consultants
Project Type:
Quay wall using concrete blocks and dredging
Main sub-consultants:
Modern Engineering Consulting Office “MECO”
Contract Details:
Role in Contract:
Main Contractor
Contract Type:
Construction (Traditional Form)
Contract Duration:
24 Months
Completion Date:
June 2024